CITY OF HOMER
PUBLIC WORKS DEPARTMENT
Carey S. Meyer, Director Telephone:
(907)235-3170
3575 Heath St. Fax:
(907)235-3145
Homer, Alaska 99603 EMAIL : cmeyer@ci.homer.ak.us
City of Homer – Public Works
Department
PROJECT PROGRESS REPORT
October, 2003
Below is a short
description of the status of all significant 2003 projects. This long list of
projects reflects the results of the City's aggressive capital improvement
program (utilizing a variety of federal and state grants and loans, local tax
revenues, and benefited property owner participation). This report is part of an ongoing
bi-annual effort to update the community regarding the status of all
construction projects. The previous
status report was prepared in March of 2003, was provided to the City Council
in the City Manager’s Report, and has been available on the City’s web page.
Kachemak Bay Multi-Purpose Ocean Dock - The new dock is substantially complete. A few small items remain for the Contractor
to complete, including miscellaneous details and clean-up work. The Contractor has filed a lawsuit over claims
that pile driving was more difficult than expected. The City and it’s
engineering team are working together to defend against the claim. In addition to the original dock construction
project, the City is also coordinating (on behalf of the USCG) the design and
installation of a camel log, fender modifications and constant tension winches
at the Coast Guard berth. Also, the
Coast Guard has requested that a dolphin be installed near the northwest corner
of the dock to provide additional berthing integrity needed during winter storm
events and to minimize dredging costs at the berth. The permitting and construction of this
dolphin improvement are on hold. The
Coast Guard is funding all additional dock improvements. The City staff continues to exert
considerable effort regarding this project.
Deepwater
Dock Damage Repair – The
repair of the damaged deck panels was completed in November 2002. The panels were removed, inspected and minor
structural damage was repaired. The
panels were grouted back into place. The
approach trestle to the dock can again safely support log truck deliveries. The cost of this work will be borne by the
vessel causing the damage.
Deepwater Dock Crane Installation – The
new 7.5 ton crane has been installed on the Deepwater
dock and it is now being used as was intended.
High-Mast
Light Pole Replacement –
The small boat harbor high mast light that blew down near Ramp 3 will be
replaced. A second pole (to be install near Ramp 6) has been purchase, but installation
funding for this second pole has not yet been identified. Both 150’ poles are on-site. The contractor has ordered lights and
lowering mechanism, with operation of the Ramp 3 pole expected by the end of
the year.
Infiltration
and Inflow (I&I) Study –
To develop solutions to the sewer treatment plant upsets we have been
experiencing during wet weather, the City initiated a study of the sewer
collection system. Flow measuring
devices have been installed at various locations and rainfall events have been
recorded. Results of this study have
suggested that the problems are caused by inflow (from service
connections). Final study was received
in July and results will be used to formulate a plan, including creation of new
policy and regulations, formulated to eliminate unwanted surface and
groundwater contributions to the sewer collection system. These recommendations will be presented to
the City Council for review and approval.
1.0 MG Water
Storage Tank - This project was
bid early in 2003 and a notice to proceed has been transmitted to the
Contractor. The total construction cost
of this project is anticipated to be $1,280,000. The project is now complete. The tank is in operation, providing
additional storage equal to one peak day’s water usage. In addition, this storage improvement allows
the water treatment plant to operate more efficiently and provides for fire
flows and emergency demand.
Animal
Shelter - The Council
approved the award of the design contract in October 2001. A design review committee of various animal
advocates, facility users, community members, and City representatives met to
provide comments to the conceptual plans presented by the architect. Cost estimates were prepared for the approved
conceptually designed facility to define appropriate work scope and budgetary
constraints. The original site proposed
for the shelter could not be acquired and alternative sites for the new
facility were evaluated. Currently, the
project is proposed to be constructed at the same location as the existing
shelter. The building is being
re-conceptualized for placement on the existing site in a manner that minimizes
earthwork, construction costs, and the impacts of construction on the existing
shelter. Much of the funding for this
project is in place, but some additional funding will most probably be
required.
Homer Public Library Project – The architect has been selected. The Library Advisory Board, along with
interested community members, are currently involved
in developing space utilization criteria for the building. Conceptual site plans will be developed from
that and presented to the community and the City Council before the end of the
year. The schedule calls for 65% design
to be completed by August 2004 (to allow construction funding acquisition
efforts to be initiated) and 100 % design will be complete by February 2005. If construction funding can be obtained, the
Library could be open in the Fall of 2005.
Jack Gist Recreational Park Improvements - The recreational park site has been
prepared in anticipation of approximately 60,000 cubic yards of fill being
placed on the site as part of the ADOT East End Road Improvement project. The street right-of-way providing access to
the site has been cleared (mostly with volunteer efforts), a drainage system
has been installed (funded by KPB), and coordination with ADOT to define fill
and access requirements has been finalized.
A grant has been obtained to build the softball fields once ADOT awards
the construction contract and the fill has been placed. We had hoped that construction of the ADOT East End Road project would begin to years, but it now
looks like the road project will begin this summer (2004). The softball field improvements could
potentially be installed the following year, with the first full season of use
in 2006.
Ocean
Drive
Bluff Erosion Control –
This project is complete. As soon as all
costs have been determined, the assessment district will be formalized. The final assessment roll will be approved by
the City Council before the end of the year.
Bond to finance the cost of the project are
currently being secured. A letter will
be sent to all property owners, responding to the questions and issues raised
at the public meeting in October.
Deep Water
Dock Corrosion Repair –
A structural engineer has inspected the condition of the Deep Water Dock and
confirmed significant corrosion problems. The engineer has completed a detailed
corrosion study, including an analysis of the adequacy of the existing cathodic protection system.
The engineer is currently preparing construction bid documents to
install an improved cathodic protection system. This work is expected to be complete next
summer. Future work may include adding
pile coatings and other repairs to prolong the useful life of the structure.
Jenny Way
Road LID - Additional gravel placed in the road three
years ago by Public Works has improved the conditions that existed when the LID
was formulated. Progress on this project
has slowed, with right-of-way acquisition and staff time issues being the main
constraint.
Homer Water
and Sewer Master Plan 2003
– The engineering firm has been selected, a contract has been executed, and
the firm has initiated plan preparation.
This effort includes creating a computer model of the existing water and
sewer system, identifying how service can be most effectively extended into
areas not currently served, determining what improvements to the existing
system will be needed to support expansion, define the cost and suggest a
schedule for necessary future capital improvements, and incorporate water and
sewer data into the City's GIS
information system. The water treatment
plant, fire flow transmission, distribution, and storage capacities will be
evaluated. The sewer treatment plant,
piped collection system and pump station capacities will be evaluated. The computer models prepared as part of this
plan will allow the City to understand (before development occurs) what impact
it will have on the existing sewer and water system. The availability of aerial photography and
topographic contour elevation information obtained as part of the new wetland
study will facilitate the effective development of this plan.
West
Lakeshore Drive
Water and Sewer LID – This project is complete. Water and sewer mains installed as part of
this LID are operational and property owners can make connections. The sewer pump station that existed in this
neighborhood has now been removed and all wastewater flows by gravity over to
the Lake Street
main. The final assessment roll has been
approved by the City Council and all benefited property has been assessed. This project is financed by the federal 2.5 %
loan secured by the City specifically for this project.
Forest Glen Water and Sewer
LID -
This project is complete. Water and
sewer mains installed as part of this LID are operational and property owners
can make connections. The sewer pump
station that existed in this neighborhood has now been removed and all
wastewater flows by gravity over to the Lake Street main. The final assessment roll has been approved
by the City Council and all benefited property has been assessed. This project is financed by the federal 2.5 %
loan secured by the City specifically for this project.
Harrington Heights Water and Sewer LID – This project is
complete. Water and sewer mains
installed as part of this LID are operational and property owners can make
connections. The final assessment roll
has been approved by the City Council and all benefited property has been
assessed. This project is financed by
the federal 2.5 % loan secured by the City specifically for this project.
Mariner Drive/Starboard Drive Water and Sewer LID - This project is complete. Water and sewer mains installed as part of
this LID are operational and property owners can make connections. The final assessment roll will be presented to
the City Council and all benefited property has will be assessed. This project is financed by the federal 2.5 %
loan secured by the City specifically for this project.
Hillside Acres Water and Sewer LID – The design of the Hillside Acres
project continues with final plans being prepared, necessary easements being
acquired, and environmental permits being obtained. The recent rejection of the Saltwater Drive water and sewer LID required some
additional design work to provide sewer service to the LID. Construction of this project will start early
in 2004 and be complete late this summer.
Thomson Drive
Sewer LID – The design of these improvements is complete
and the plans have been approved by ADEC for construction. The project was bid with the ADOT
East End Road project this summer
(2003) and construction of the sewer mains will be completed with the road
improvement project (expected to be initiated and completed next summer, 2004).
East End Road
Sewer LID - The design of these improvements is complete and
the plans have been approved by ADEC for construction. The project was bid with the ADOT
East End Road project this summer
(2003) and construction of the sewer mains will be completed with the road
improvement project (expected to be initiated and completed next summer, 2004).
East End Road Water and Sewer Extensions -
As the design of the ADOT East End Road improvements is being completed by the
state, the City has made an effort to identify any water and sewer improvements
that may be required in the future along the alignment of the proposed road
project. Public Works has been working
with ADOT to include in the project the lowering of existing water and sewer
mains that conflict with the new road elevations and to make sure that future
road crossings and future service lines adjacent to our existing mains are
constructed as part of the project. The
City has also contracted for the design of the extension of the existing water
and sewer main out to Kachemak
Drive. Construction of
these main extensions can be accomplished cheaper as part of the ADOT
improvement than after road construction is complete. Funding for the main extensions has been
obtained through the federal Clean Water/Drinking Water loan program discussed
above. Recommendations regarding how
benefited property owners will pay for their fair share of the extensions will
be presented to the City Council soon.
Various
Road, Water and Sewer LID Petitions – The formation of many water
and sewer LID’s are requested by the public. The following is a list of projects for which
boundaries have been established, conceptual designs have been completed, cost
estimates have been prepared, and petitions have recently been, are or will
soon be circulated:
Jeffrey
Avenue Road Reconstruction and Paving
Lakeshore
Drive Road Reconstruction
Harrington
Heights Road Reconstruction (rejected by majority of property owners)
Bell Avenue Road
Reconstruction and Paving
Cook’s
Way Water and Sewer
Latham Lane Sewer
Rosebud Court Water and Sewer (rejected during
objection period)
Kachemak Drive Water and Sewer - Phase I (currently in
objection period)
Kachemak Drive Water and Sewer - Phase II (rejected during
objection period)
Ocean Drive Loop Road Sewer and Water
Mission Road Sewer
ADOT
Bartlett Street Road Improvements – The ADOT is finishing the design of
road improvements for Bartlett Street from Pioneer Avenue to the hospital; and Hohe
Street from Fairview up to the hospital. This project will
also include the replacement of the water line under Bartlett and Hohe. The City is
responsible for coordinating the design of the water main replacement. The latest STIP list calls for construction
in 2005.
ADOT
East End Road Improvements (MP 0.0-3.75) – This project was bid by ADOT this
summer and the contractor has been given notice to proceed. The contractor is completing survey and
clearing work in anticipation of some winter utility work, but no significant
earthwork is expected until Spring 2004. Construction of this improvement will most
probably be completed by the fall of 2004.
Homer Skateboard Park – The new skateboard park has been paved
and the facility is being used with the permanent ramps that were purchased
through a community funding effort.
Signage has been installed. The
mural/site sign and benches are planned to be installed as soon as the mural
has been finished and benches have been acquired. No additional obstacles, makeshift items or
modifications to the existing ramps will be permitted.
Implementation
of Beach Policy Task Force Recommendations – The City identified a Coastal Impact Assistance program
grant and made application for funds to implement regulatory and educational
signing installation, and access restriction/parking improvements. The City was awarded a grant for $75,000 for
beach access restriction improvements and regulatory signing. Public Works has submitted to the Corps of
Engineers a permit application (revised to reflect no fill placement) to
construct two small parking areas along the east side of Homer Spit Road. All improvements were completed this
summer.
City
Beautification Efforts –
The City produced over 10,000 plants for use in City and local business
planting areas. A riding mower has been
acquired to provide for more efficient and more often mowing of large lawn
areas like Triangle Park, the Hazel Street property, and other park sites. The Parks and Recreation Department secured
the use of a 200 gallon tank (mounted in pick-up truck) to make watering of
City gardens more efficient and the community more beautiful. Baycrest Park received much acclaim this year,
producing exceptional color and a wide variety of annual and perennial flowers.
The other beds and park area around the City were given tender love and care by
the Parks and Recreation department, adding color to summer activities. The Public Works Department will continue to
assist businesses develop planting areas and expand and improve the City’s
public planting spaces. The cold frame
(used to harden City grown flower plants) was moved to eliminate snow plowing
conflicts at the high school.
New educational
signage was installed at Bishops Beach (signs provided by USF&W,
installation by City crew).
Spit Restrooms – Utilizing a
combination of City and State funds, Public Works will attempt to construct
three new restrooms on the Spit. A
restroom will be constructed near Ramp 6 on the west side of the harbor (work
will be done to try to reduce the cost of this facility. Construction of the reworked project will
occur next summer. As funds permit, the
restroom at Ramp 4 will be demolished and a new facility will be constructed on
the east side of the small boat harbor to replace it. State funds will be used to construct a small
restroom near the Fish Dock for the use of commercial fisherman and dock
workers.
Large Equipment Storage Shed
– The design of a 12-bay shed to store large construction equipment has been
designed. The intention is to maximize
the use of available City owned material and crew labor to construct the facility. Funds are being sought to purchase the
foundation and roofing materials.
Fire, Police, Airport Terminal Bldg Painting
– The fire department, police department, and the airport terminal buildings
received a fresh cost of paint/stain this summer.
Pioneer Cemetery Fence – A new fence was
installed around the Homer Community Cemetery (Pioneer Cemetery). This fence was purchase out of last year’s
budget and installed by Parks and Recreation staff with significant assistance
from Public Works crews late this summer.
Flood Damage Repair- The following “projects” are complete or in the process of
being completed. FEMA disaster
assistance funding will pay for most all of this work:
Fairview Ave./Woodard
Creek This
project included the repair of road embankment erosion, culvert repair, debris
removal and headwall construction.
Road Repair by City Crews This work represent the work of City
employees who responded to the immediate need to repair roads and drainage
system damage.
Debris Removal by City Crews This work completed by City crews included
all labor and equipment time necessary to remove debris and deal with the
immediate implications of the flood.
Emergency Protective Measures by City Crews This work
included work to protect infrastructure from damage during the event.
Fishing Hole Repair/Spit Pathway
Embankment Repair
This work included cleaning up the Fishing Hole facility, removing
debris and repairing damage.
Island View Water Main/Winding Trails
Sewer Main
Repair This
work includes rebuilding embankments eroded by the flood, which exposed water
and sewer mains.
Ben Walters Park Boardwalk Repair This work included
relocation of the timber boardwalk after it was blown out of alignment.
Road to Reservoir Repair This work included repairing erosion damage
to the road to the reservoir.
Mattox Street Drainage Repair This work included repairing
erosion along Mattox Street, replacing ditch with culvert.
Seawall Flood Repair This work included diversion of surface
water away from the bluff, replacement of damaged wall section and replacement
of lost backfill.
Paradise Place and Saltwater Drive
This work included replacement of damaged culverts and repair of eroded
road embankment.